| 
       
        
       
	  ENSURING THROUGHPUT IN POLANDComplex Pipeline Refurbishment Program 
	  Delivers Major Gains
 
       
	  Dec 08, 2014 + + + Keeping hundreds of miles of Poland’s pipelines flowing 
	  at optimum capacity isn’t easy. It’s a demanding job, requiring great care 
	  and attention to planning and executing the rigorous maintenance programs 
	  necessary to ensure that every line is clean and free of defects, 
	  especially those that could eventually cripple production. A recent 
	  pipeline refurbishment program carried out by a major gas transmission 
	  operator in the mountains of eastern Poland, along the Ukraine border, 
	  illustrates the complex nature of maintaining pipelines.
 In keeping 
	  with its commitment to maintaining the integrity of Poland’s gas 
	  transmission system, the operator commissioned a comprehensive cleaning 
	  and inspection of a 28-inch diameter, 11 km (6.8 mi) section of a 40 km 
	  (24.8mi) pipeline, which was commissioned in the early 1970s. The 
	  pipeline, which is part of Poland’s natural gas network, is particularly 
	  important because it can support an interconnector to and from the 
	  Ukraine.
 
 Having partnered on many pipeline operations over the last 
	  20 years, T.D. Williamson (TDW) was commissioned to execute the program, 
	  which was completed in August 2014. As a result of the complex pipeline 
	  cleaning, gauging and inline inspection (ILI) activities, the operator 
	  reaped a number of benefits, including increased product flow and enhanced 
	  pipeline integrity.
 
 The advantages to the operator are 
	  far-reaching. Because the line is clean and free of debris that impeded 
	  flow, there is a much higher flow rate. This means that associated 
	  production costs are lower and transmission is more efficient. Looking 
	  ahead, the operator’s repair costs will also be reduced because the ILI 
	  data produced by the inspection flags defects, making it possible for the 
	  operator to address them as needed. Potential damage otherwise incurred by 
	  these defects is mitigated, reducing future associated maintenance costs 
	  and downtime.
 
 Cleaning, gauging & inspecting
 
 When TDW was 
	  contracted to clean the 28-inch diameter line that runs through the Polish 
	  mountain range, the line was operating at a pressure of 38 barg, at an 
	  average flow of  75,000 m2 per hour. It was deemed unpiggable because it 
	  was so choked by debris that a pipeline cleaning or inspection pig would 
	  be unable to pass. Further complicating the situation, a visibility study 
	  carried out by TDW before cleaning and inspection revealed a section of 
	  the line with eight acute miter bends, making it impossible for the pigs 
	  to navigate and clean, let alone inspect.
 
 Working in cooperation 
	  with the operator, TDW developed a solution. To address the problem, 
	  custom-designed temporary pig launchers and receivers were built and 
	  welded at strategic points along the line. To prevent a pig from being 
	  lodged in the miter bends, these sections were removed and replaced with 
	  pipe that would accommodate the cleaning and inspection pigs. All pigs 
	  scheduled for use during the program were fitted with transmitter units 
	  that the crew would use to track their progress. Finally, to verify the 
	  piggability of the line and ensure that its cleaning pigs and inspection 
	  tools would be capable of negotiating the pipeline, TDW performed a gauge 
	  pig run. Once this was successfully completed, preparations were made to 
	  proceed with the first of the cleaning runs.
 
 Efficient cleaning 
	  clears the way
 
 To clean the lines, a five-step cleaning program was 
	  carried out by TDW with 24 specially selected cleaning pigs. After 
	  completing 23 runs, the 11 km (6.8 mi) line, which had been so congested 
	  it was unpiggable, was clean and free of debris. Before cleaning, 
	  production had been sluggish. As a result of the cleaning, TDW cleared 
	  approximately 3.5 tons of silt, timber, metal fragments, welding rods and 
	  pipelaying equipment, allowing gas to flow much more freely.
 
 Satisfied that the line had been thoroughly cleaned, TDW proceeded with 
	  the next phase: an inline inspection of the 11 km (24.8mi) section of the 
	  line. Working closely with the operator‘s team, TDW executed inspection 
	  runs on the line during a three-week period in August 2014. TDW used a 
	  number of its high-resolution inspection tools to inspect the pipeline, 
	  including deformation (DEF) technology for geometric anomaly inspection, 
	  Gas Magnetic Flux Leakage (GMFL) inspection technology for corrosion 
	  inspection, and the XYZ Inertial Measurement Unit for GPS pipeline 
	  mapping.
 
 Following data validation and analysis, TDW delivered a 
	  comprehensive final report to the operator. After assessing the condition 
	  of the pipeline, as reflected in the ILI data, the operator will work with 
	  TDW to formulate plans to schedule any necessary repairs or further 
	  procedures on the line. The operator and TDW are currently discussing how 
	  this method of cleaning and inspection might be scaled and carried out on 
	  the remaining 29 km (18 mi) section of this line.
 
 The final outcome 
	  of the pipeline refurbishment program is extremely important to the 
	  operator and its efforts to assure the continued integrity of the line. 
	  “Much of the success of this program lies in the painstaking attention to 
	  inspecting the line before cleaning,” says Mateusz Bil, Project Engineer 
	  for TDW. “This is critical because it allows us to rectify trouble spots, 
	  such as the eight miter angles that would most certainly have blocked the 
	  cleaning pigs, disrupting the cleaning operation. Instead, we were able to 
	  clean the line so that it was in pristine condition, ready for the inline 
	  inspection. By doing so, the inspection runs would generate the highest 
	  quality of data, revealing potential threats to pipeline integrity,” he 
	  added.
 
 
 
       
	  Source: T.D. Williamson Polska Sp. z o.o. www.tdwilliamson.com
 
 
 
 
 
       
      
 
 
 
       
        
       
      
 
 
       
      
 
       
      
 
       
      
	  
 
 
 
 | 
        
  Worldwide more than
 90,000 paid subscriptions
 
          
        
         Worldwide 
		more than 48,000 subscriptions -
 100% one-year direct request 
		qualification
 
          
        
         'What's New' in Upstream, Midstream and 
		Downstream Products & Services. Circulation 37,000
 
         PennWell
 Petroleum Group:
 
       
        
       
       
       
       
       
       
       
      
       
        
       
       
         Oil & Gas JournalOil & Gas Journal Russia
 OGJ_eNewsletter
 OGJ-Website-Statistics
 
       
        
       
       
       
       
       
       
       
      
       
        
       
       
         
 Oil, Gas & Petrochem Equipment
 	    
       
        
       
       
         
       
        
       
       
       
       
       
       
       
      
       
        
       
       
         Offshore Magazine Offshore 
		Russia
 Offshore eNewsletter
 Offshore 
		Website Statistics
 
 Oil & Gas Financial Journal
 
 
 
       
        
       
       
       
       
       
       
       
      
       
        
       
       
       + + + 
       
        
       
       
         For more information, media
        kits or
        sample copies please contact Andreas 
		Sicking
 +49 (0)2903-338570
 wilhelms@pennwell.com
      
       
        
       
       
      
       
        
       
       
        www.sicking.de
 
		
		
       
        
       
       
        
 |